Tab Article
To enable users to understand the operation of the Engineering and Construction Contract, this book contains flow charts which set out the procedural logic of the 75 clauses that can be presented with benefit by flow charting.
To enable users to understand the operation of the Engineering and Construction Contract, this book contains flow charts which set out the procedural logic of the 75 clauses that can be presented with benefit by flow charting.
Flow Charts
Chapter 1 : Communications
Chapter 2 : The Project Manager and The Supervisor
Chapter 3 : Adding to The Working Areas
Chapter 4 : Early Warning
Chapter 5 : Ambiguities and Inconsistencies
Chapter 6 : Illegal and Impossible Requirements
Chapter 7 : Prevention
Chapter 8 : Providing The Works
Chapter 9 : The Contractor?S Design
Chapter 10 : Using The Contractor?S Design
Chapter 11 : Design of Equipment
Chapter 12 : People
Chapter 13 : Working With The Employer and Others
Chapter 14 : Subcontracting
Chapter 15 : Other (Contractor) Responsibilities
Chapter 16 : Starting, Completion and Key Dates
Chapter 17 : The Programme
Chapter 18 : Revising The Programme
Chapter 19 : Access to and Use of The Site
Chapter 20 : Instruction to Stop Or Not to Start Work
Chapter 21 : Take Over
Chapter 22 : Acceleration
Chapter 23 : Tests and Inspections
Chapter 24 : Testing and Inspection Before Delivery
Chapter 25 : Searching for and Notifying Defects
Chapter 26 : Correcting Defects
Chapter 27 : Accepting Defects
Chapter 28 : Uncorrected Defects
Chapter 29 : Assessing The Amount Due S
Chapter 30 : Payment
Chapter 31 : Defined Cost
Chapter 32 : The Contractor?S Share (Option C and D)
Chapter 33 : The Activity Schedule (Option A and C)
Chapter 34 : The Bill of Quantities (Option B and D)
Chapter 35 : Compensation Events
Chapter 36 : Notifying Compensation Events
Chapter 37 : Quotations for Compensation Events
Chapter 38 : Assessing Compensation Events
Chapter 39 : The Project Manager?S Assessments
Chapter 40 : Implementing Compensation Events
Chapter 41 : The Employer?S Title to Plant and Materials
Chapter 42 : Marking Equipment, Plant and Materials Outside The Working Areas
Chapter 43 : Removing Equipment
Chapter 44 : Objects and Materials Within The Site
Chapter 45 : Employer?S Risks
Chapter 46 : Contractor?S Risk
Chapter 47 : Repairs
Chapter 48 : Indemnity
Chapter 49 : Insurance Cover
Chapter 50 : Insurance Policies
Chapter 51 : If The Contractor Does Not Insure
Chapter 52 : Insurance By The Employer
Chapter 53 : Termination
Chapter 54 : Reasons for Termination
Chapter 55 : Procedures on Termination
Chapter 56 : Payment on Termination
W1 Dispute Resolution (Used Unless Option Y(UK)2 Applies)
W2 Dispute Resolution (Used When Option Y(UK)2 Applies)
X1 Price Adjustment for Inflation (Used Only With Options A, B, C and D)
X2 Changes In The Law
X3 Multiple Currencies (Used Only With Options A and B)
X4 Parent Company Guarantee
X5 Sectional Completion
X6 Bonus for Early Completion
X7 Delay Damages
X12 Partnering
X13 Performance Bond
X14 Advanced Payment to The Contractor
X15 Limitation of The Contractor?S Liability for His Design to Reasonable Skill and Care
X16 Retention (Not Used With Option F)
X17 Low Performance Damages
X18 Limitation of Liability
X20 Key Performance Indicators (Not Used With Option X12)
Y(UK)2 The Housing Grants, Construction and Regeneration
Act 1996
Y(UK)3 The Contracts (Rights of Third Parties) Act 1999